Berth 2 Primary Coal Sampler Replacement

Project Category: 
Location: 
Delta, B.C
Customer: 
Westshore Terminals Ltd.

Westshore Terminals Ltd. contracted LNS to replace their existing primary coal sampler located on Berth 2.  LNS installed a new falling stream sampling system that allows Westshore Terminals Ltd. to comply with industry standards for quality control. This project included the design and installation of structural modifications to Transfer Tower 5 and the installation of a new spoon and skirting system, new headbox and vibrator trays as well as two movable magnets complete with trolley and track systems.  LNS and its subcontractors completed this project within a scheduled maintenance shutdown with zero recordable safety incidents.